HRC Construction General Contractor
VALUE: $5.1 million
OWNER: City of Surrey
DATE: February to June 2011
CONSULTANT: Associated Engineering
SUPERVISOR: Mark Reid
DESCRIPTION: new pedestrian bridge
Here's a sample of completed projects. Click on thumbnail to view larger image.
VALUE: $5.1 million
OWNER: City of Surrey
DATE: February to June 2011
CONSULTANT: Associated Engineering
SUPERVISOR: Mark Reid
DESCRIPTION: new pedestrian bridge
VALUE: $2.5 million
OWNER: Penticton Indian Band
DATE: May to November 2013
CONSULTANT: Klohn Crippen Berger
MANAGER: Merv Parr
SUPERVISOR: Mark Reid/Kenton Regehr
DESCRIPTION: remove old earth dam and install new engineered earth dam, complete with spillway and channelization
KUDOS: project was nominated for environmental achievement by the ACEC-BC
VALUE: $3.5 million
OWNER: Township of Langley
DATE: April 2014 to June 2015
CONSULTANT: Associated Engineering
MANAGER: Merv Parr
SUPERVISOR: Mark Reid
DESCRIPTION: construction of potable water booster pumping station and a pressure reducing station for East Langley Water Supply Project
VALUE: $2.1 million
OWNER: BC Ministry of Highways
DATE: June 2015 to November 2015
CONSULTANT: Associated Engineering
SUPERVISOR: Mark Reid / Skyler Dufort
DESCRIPTION: On the Coquihalla Hwy, Peers Creek Bridge deck replacement by using Hydro-Demolition methods and placing new steel-fibre reinforced concrete. Ongoing challenges of traffic management and working in a sensitive environmental area. Works included heavy civil construction and large diameter process piping.
VALUE: $5.5 million
OWNER: Pacific Coast Terminals / K+S
DATE: March 2016 thru June 2017
CONSULTANT: CH2M Hill Canada
SUPERVISOR: Skyler Dufort
SITE COORDINATION: Andrew Franklyn
PROJECT MANAGER: Merv Parr
SITE SAFETY COORDINATIOR: Shane Rodgers
DESCRIPTION: Port Moody, two new substation structures, 3KM of new duct bank, conveyor footings and wastewater systems.
VALUE: $2.5 million
OWNER: BC Hydro
DATE: February to December 2013
CONSULTANT: AMEC
MANAGER: Merv Parr
DESCRIPTION: renovation and addition of CBs and controls