HRC Construction General Contractor
VALUE: $1 million
OWNER: TransLink
DATE: April 2018 to June 2020
CONSULTANT: PBS Consulting
SUPERVISOR: Andrew Franklyn
PROJECT MANAGER: Merv Parr
DESCRIPTION: TransLink Rectifier Stations - MetroTown
VALUE: $5.5 million
OWNER: Pacific Coast Terminals / K+S
DATE: March 2016 thru June 2017
CONSULTANT: CH2M Hill Canada
SUPERVISOR: Skyler Dufort
SITE COORDINATION: Andrew Franklyn
PROJECT MANAGER: Merv Parr
SITE SAFETY COORDINATIOR: Shane Rodgers
DESCRIPTION: Port Moody, two new substation structures, 3KM of new duct bank, conveyor footings and wastewater systems.
VALUE: $1.5 million
OWNER: BC Hydro
DATE: October 2015 to June 2016
CONSULTANT: AMEC / Foster Wheeler
SUPERVISOR: Skyler Dufort
PROJECT MANAGER: Merv Parr
DESCRIPTION: Construction of a massive blast-wall along the south side of the substation. Work took place in operating substation and required specialized pile driving techniques and concrete and steel erecting procedures. Work also included fire code upgrades and access walkways.